|
|
|
|
|
|
Decision Session – Executive Member for Transport
|
15 November 2022 |
Report of the Director of Transport, Environment and Planning |
Active Travel Programme – People Streets / Ostman Road
Summary
1. 3 preliminary designs that offer pedestrians and cyclists a more appealing, safer environment by which to access Carr Infants and Junior schools have been generated.
2.
A decision is required to take this
scheme through to Detailed Design, while further funding support is
being sought.
The Executive Member is asked to:
3. Approve Option 1 – Approve the progression of the proposed design option presented in Annex A through to detailed design. Incorporate this work into a future bid for additional scheme funding.
4. Reason:
Progressing this scheme through detailed design will result in a ‘shelf-ready’ scheme that will be more likely to attract future funding, thereby increasing the chances of delivery on the ground.
Background
5. The Active Travel Programme aims to improve the amenity and safety of active travel forms such as walking and cycling, promoting the adoption of healthier, more environmentally friendly travel.
6. In 2020, Sustrans carried out a one day trial in which temporary build-outs were placed outside Carr Junior school during peak times to discourage parents from parking outside schools and make the roads safer for children. The trial was popular amongst parents and residents interviewed, and was deemed a success. In response to the Sustrans trial’s success, the Active Travel Programme launched this scheme.
7. In the February 2022 Executive Member Decision Session, the Executive Member for Transport approved the Project Outline for this scheme (Background Paper 1).
8. Feasibility work has been completed and a summary report can be found in Annex I.
9. This report concludes that none of the proposed options are affordable within current budgets, however the recommendation is to seek additional grant funding at the next round of Active Travel funding to allow the scheme to progress to delivery. To achieve this, it is preferable to have a ‘shelf-ready’ scheme, which is more likely to attract funding than a proposal at the preliminary design stage.
10. To strengthen the bid for funding and to not further delay implementation, officers seek approval to progress the lowest cost design option, presented in Annex A, through Detailed Design.
11.
An electronic consultation has been
carried out with local ward councillors for Acomb and external
stakeholders. Targeted external stakeholders included residents and
businesses on and in the immediate vicinity of Ostman Road, and
parents and staff affiliated with Carr Infant and Junior
Schools.
12.
Refer to Annex G for a summary of
the consultation responses received.
13.
The majority of respondents (53%)
used the street to drop off and collect children from school. Cars
were the most prevalent mode of transport used by respondents
(43%), with walking the second most common mode (39%) and cycling
third (12%).
14.
Asked about the conditions for
pedestrians and cyclists, the responses indicated that the current
provision is not good. Most respondents agreed that action needed
to be taken to improve pedestrian safety and amenity on Ostman
Road.
15.
The purpose of this scheme is to
encourage people to walk and cycle to school by improving
conditions. 40% of respondents said they would walk / cycle instead
of driving if conditions improved. 36% of respondents were
undecided on this question, and 25% of respondents indicated they
would not change modes even if conditions were improved.
16.
This feedback suggests that there is
a real possibility of influencing people’s behaviour and that
there is a level of support for interventions to re-prioritise the
roadspace. There were however several concerns relating to how that
would be achieved.
17.
In terms of potential changes to
restrictions there was no single option that gained majority
support, with a restriction on peak time parking being the most
popular (47%). 24% of respondents did not support any form of
additional parking restrictions.
18.
There were several doubts that
parking restrictions would be enforced, with concerns raised that
those restrictions that are currently present are not effectively
enforced. This is a valid concern that will be investigated in more
detail at the next stage of the scheme, however officers are
confident that an effective enforcement arrangement can be
implemented.
19.
A common piece of feedback was that
parking restrictions would move traffic and parking to neighbouring
streets. This is likely correct; based on the consultation feedback
officers believe a certain portion of motorists would still drive
even if conditions were improved for pedestrians and cyclists. This
should be seen as one of the primary downsides of this scheme and
officers are not able to offer a complete mitigation to this issue.
As with all parking restrictions in the city, there would be an
unavoidable level of traffic redistribution.
20.
On this point, a common piece of
feedback was that a number of respondents indicated that they had
no alternative to driving, whether due to their work schedule or
other related practicalities. This is understood and it should be
understood that this scheme will significantly disbenefit some
motorists.
21.
Several consultees responded with
specific feedback relating to their disability. It should be noted
that there were a significant number of these responses that are
not included within the attached annex due to the fact that they
contained personal data. These responses will be given special
consideration here.
22.
This feedback generally indicated
that they didn’t feel they would be able to access the school
at all if restrictions on parking were introduced, either due to
mobility related disabilities or due to the specific disabilities
of their children, for example learning disabilities. The impact on
these users is different to the impact on general motorists and is
potentially much more significant.
23.
It is therefore proposed that when
the parking restrictions are turned into a formal Traffic
Regulation Order that exemptions are considered to ensure that
users with disabilities appropriately considered. The feedback from
this consultation process has been especially helpful in this
regard and further more targeted consultation and assessment of any
impacts on this issue will be undertaken prior to
implementation.
24.
Another common point raised by
residents of Ostman Road and neighbouring streets was a feeling
that they should have some form of priority or special
consideration on the street by merit of being a resident. The
primary purpose that this is usually achieved is by means of a
residents parking scheme, however this is not being proposed in
this case.
25.
There were several responses that
suggested removal or diversion of bus services would improve the
situation because buses often get caught up in the traffic and
contribute to the congestion.
26. It is accepted that buses do get caught up in traffic and block the street on occasion, however officers do not support the idea of solving this issue by restricting bus access. Public Transport is senior to car borne commuting on the Council’s Road User Hierarchy, and therefore it is proposed that a more strategically consistent approach is to restrict the motor vehicle side of the issue rather than the buses.
Options
27. Option 1 - Note the outcome of the feasibility work for the ‘People Streets at Ostman Road’ scheme laid out in this report and decide to seek further funding before proceeding to implementation. Seek Active Travel grant funding support at the next round of bidding. Progress with detailed design work on ‘Design Option 1’ described in the attach Feasibility report, in advance of receiving additional funding.
Analysis
28.
The attached Feasibility report (Annex I) explores
3 preliminary design options that each achieve the objectives of
the scheme, but have slightly differing features and cost
estimates.
29. Cost Estimates Table
|
Design 1 |
Design 2 |
Design 3 |
Preliminary design (already incurred) |
£32,239 |
£32,239 |
£32,239 |
CYC internal costs (already incurred) |
£1633 |
£1633 |
£1633 |
Other (already incurred) |
£2102 |
£2102 |
£2102 |
Further design and development |
£58,794 |
£64,873 |
£83,308 |
Construction |
£419,959 |
£463,380 |
£595,055 |
Risk margin |
£191,501 |
£211,302 |
£271,345 |
|
|
|
|
Total |
£706,228 |
£775,529 |
£985,682 |
30.
There are insufficient funds within
the budget to deliver any of the proposals. It is therefore
recommended that additional funding
from the next round of government Active Travel grants is sought
prior to implementation.
31.
Such a bid would be more likely to
be successful if CYC could present a ‘shelf-ready’
scheme with most of the work complete, instead of a broad outline
of intentions. The work that has already been completed goes a long
way to achieving this, however progressing a specific design
proposal to the detailed design stage would go even further to
achieving this aim.
32.
Officers are recommending that Design Option 1
within the attached report is progressed to detailed design
immediately following this decision session. This option achieves
the objectives of the project and is the cheapest of the proposals,
which will go some way to improving the chances of receiving
additional funding.
33.
The traffic regulation order that is
proposed to be included within the detailed design is a peak-time
no-parking zone. This is the restriction that received the most
support in the consultation process and officers are confident that
it can be implemented in a way that will achieve the objectives of
the scheme.
34.
Trialling a traffic restriction
prior to any built environment changes is not being offered as an
option. Advice from the Principal Designer indicates that the built
environment changes are an essential part of the scheme in terms of
achieving the objectives, and a trial without the physical changes
would not be successful, nor would it provide any valuable
learning.
35.
Recorded personal injury accident
data shows there was one incident in this location,
‘slight’ in severity, recorded between 01/01/2017 and
31/12/2021. The incident occurred between a moving vehicle and a
parked car. This does not represent a significant trend that can be
directly addressed, however design proposals were still created
with safety as a priority consideration. Also, despite there not
being a significant safety issue recorded on the street, the
objectives of encouraging modal shift remain pertinent.
36.
Replication of the 2021 Sustrans
trial design layout was considered however it was found that this
layout could not be implemented permanently to a high standard due
to the fact that the carriageway is constructed of jointed
concrete, therefore making such a solution extremely
cost-prohibitive.
37.
The recommended design solution
includes the following features:
Gateway markings to indicate a changed priority space and to make
restrictions more visible.
Introduction of a peak-time parking restriction between gateway
features.
Replacement of concrete footway with improved surface to allow
implementation of a shared space facility.
Planting features, benches and public realm improvements to make
the route more desirable for active travel users, to encourage
modal shift.
Installation of 2 new parallel pedestrian and cycle
crossings.
Installation of benches and planting to improve public realm,
therefore encouraging modal shift.
Renewal of existing road cushions and speed tables.
38.
Implementation of the proposed
changes requires the removal of a number of trees. It is proposed
to replace these trees, and in greater number.
39.
Existing conditions and all design
proposals scored Amber on the LTN 1/20 Junction Assessment Tool
(JAT). This is due to the only significant junction change being
the continuous footway. However, due to the quiet nature of the
street, the proposed facilities are considered appropriate.
40.
Due to the fact that this scheme is
intended to be funded through a government grant, the requirements
of LTN 1/20 are especially relevant. Officers are confident that
the proposed solution does offer a significant improvement, and
that the reasoning provided to Active Travel England via the bid
process will be sufficient to address this issue.
41.
Existing conditions on Ostman Road
scored below the 70% pass threshold at 66% on the LTN 1/20 Cycling
Level of Service (CLoS) assessment. Design 1 would increase this
score to a pass score of approximately 76%.
42.
Surveys carried out on Ostman Road
revealed that the majority of pedestrians cross near to the school
entrances where there is currently a high occurrence of illegal
parking. The TRO restricting parking within the gateway features
will reduce the number of parked vehicles, clearing the road and
making it safer and easier for pedestrians to cross.
43.
Parallel crossings will make it
safer and easier for pedestrians to cross the road, as they will be
given priority.
44.
The enhanced buffer will further
separate children from the road, making it easier for parents to
safely walk or cycle them to school.
45. Traffic flows along Ostman Road are considered low, meaning that cyclists can use it as an on-street quiet route in line with LTN 1/20 standards. The widened shared footway on the north and south sides of the road also offer space for children to cycle safely beside their parents.
Council Plan
46. Proposed changes will encourage active travel and move priority towards pedestrians, providing children and parents with a safer, greener way of getting to school. Therefore carrying out these works contributes to the ‘Getting around sustainably’ key outcome of the Council Plan.
Implications
Financial
47. The Active Travel programme is funded from a combination of grant funding and council resources allocated through the capital programme. The recommended options within the report maintain the programme within the available budget. This is in line with the previous decision to prioritise schemes once costs were known for individual schemes. Where schemes cannot be delivered DfT confirmation will be needed before the grant funding can be reallocated.
Human Resources (HR)
48. There are no HR implications
Equalities
49.
The Council needs to take into
account the Public Sector Equality Duty under Section 149 of the
Equality Act 2010 (to have due regard to the need to eliminate
discrimination, harassment, victimisation and any other prohibited
conduct; advance equality of opportunity between persons who share
a relevant protected characteristic and persons who do not share it
and foster good relations between persons who share a relevant
protected characteristic and persons who do not share it in the
exercise of a public authority’s functions).
An Equalities Impact Assessment has been carried out and is annexed
to this report at Annex H.
Legal
50.
The It is the duty of a local
authority to manage their road network with a view to achieving, so
far as may be reasonably practicable having regard to their other
obligations, policies and
objectives, the following objectives:
(a) securing the expeditious movement of traffic on the
authority’s road network; and
(b) facilitating the expeditious movement of traffic on road
networks for which another authority is the traffic
authority.
Local authorities have a duty to take account of the needs of all
road users, take action to minimise, prevent or deal with
congestion problems, and consider the implications of decisions for
both their network and those of others.
If the decision is made to give permanent effect to the temporary
traffic order in this report, the decision maker should consider
the criteria contained within section 122 of the Road Traffic
Regulation Act 1984 and in particular the duty to make decisions to
secure the expeditious, convenient and safe movement of vehicular
and other traffic (including pedestrians).
Crime and Disorder
51. There are no Crime and Disorder implications.
Other
52. Disruption during construction – Constructing this scheme inevitably means a certain level of work on the adopted highway, with an associated level of delay and disruption to pedestrians and vehicular traffic. Such works will be scheduled and planned to minimise this disruption, and sufficient information and notice will be given to affected parties.
Risk Management
53. Every project within the Active Travel Programme is managed in line with the Corporate Risk Management Strategy. This involves action by assigned Project Managers to identify, manage, and mitigate specific risks to delivery.
Contact Details
Author: |
Chief Officer Responsible for the report:
|
|
|||||
Christian WoodProgramme ManagerChristian.wood@york.gov.uk |
James GilchristDirector of Transport, Environment and Planning
|
||||||
Report Approved |
√ |
Date |
07/11/2022 |
||||
|
|||||||
|
|
|
|
||||
Wards Affected: Acomb Ward |
|
||||||
|
|
|
|||||
For further information please contact the author of the report |
|
|
|||||
|
Background Papers:
Background Paper 1 – Active Travel Programme – July 2022
https://democracy.york.gov.uk/ieListDocuments.aspx?CId=738&MId=13548&Ver=4
Annexe A – Preliminary Design 1
Annexe B – Preliminary Design 2
Annexe C – Preliminary Design 3
Annexe D – LTN 1/20 Cycling Level of Service
Annexe E – LTN 1/20 Junction Assessment Tool
Annexe F – Ostman Road School Street Audit
Annexe G – External Consultation Details
Annexe H – Equalities Impact Assessment
Annexe I – Principal Designer’s Closure Report
List of Abbreviations Used in this Report
CYC – City of York Council
DfT – Department for Transport
ATP – Active Travel Programme
ATF – Active Travel Fund
CLoS – LTN 1/20 Cycling Level of Service
JAT – LTN 1/20 Junction Assessment Tool